I.
Erection
Procedure
Structural steel installation work
shall be performed
in accordance with following flow chart.
|
Re-Survey
|
|
|
|
|
|
|
Grain Raising ( Chipping )
|
|
||
|
|
|
|
|
Hosting
|
|
|
|
|
|
|
Installation Every 3 Colomn
|
|
||
|
|
|
|
Aligment and Leveling
|
|
|
|
|
|
|
|
|
Bolt Tightening
|
|
|
|
|
|
|
Installation of Stair and Feeder Rack
|
|
||
|
|
|
|
|
Painting
|
|
|
|
|
|
|
|
Final Chek List
|
|
|
|
Re-Survey
|
|
|
|
|
|
|
Grain Raising ( Chipping )
|
|
||
|
|
|
|
|
Hosting
|
|
|
|
|
|
|
Installation Every 3 Colomn
|
|
||
|
|
|
|
Aligment and Leveling
|
|
|
|
|
|
|
|
|
Bolt Tightening
|
|
|
|
|
|
|
Installation of Stair and Feeder Rack
|
|
||
|
|
|
|
|
Painting
|
|
|
|
|
|
|
|
Final Chek List
|
|
1.
Fabricated
Materials Handling and Storage
On receipt at Site the Fabricated
materials shall be carefully unloaded and examined for defects, checked and
sorted according to its erection sequence requirements. The steels must be
supported with wooden skids above clean and dry ground. Rafter and other
members shall be supported properly to avoid unnecessary deflection.
The steel structure members shall be
stored ad handed in such a manner that each is not subjected to excessive
stress which may cause damaged.
Bolts shall be stored in dry and
clean containers covered with water proofed sheets. Packages of bolts shall be
opened shortly before it will use.
The fabricated materials shall be
verified with respect to markings on the
match marking drawings and shipping list supplied. Any materials found damaged
or defective shall be stacked separately and the damage or defective portions
shall be indentified by paint applied in distinct color.
2.
Re – Survey
Well in advance before starting the
erection work re – survey shall be conducted in the presence of the Engineer /
Consultant and anchor erector to determine the accuracy of grid lines
dimensions, anchor bolts distances and
plumpness, level and elevations.
Non – compliance shall be corrected
prior to erection
works.
All reference and control points
shall be fixed near the work site for facilitating the erection work.
3.
Grain
Raising ( Chipping )
Before installation, grain raising
shall be performed
on upper surface of the foundation in order to avoid the flaking off of grout
materials from the foundation surface.
4.
Erection
Works
4.1 Transporting of structural steel members
All transporting and off loading
shall be carefully to the location where
it is be erect.
4.2 Man
Power Schedule
Worker for installation this steel
towers shall be high skill and
experience. Every location must be good
communication and coordination. The position for each job with the following list:
4.3 Hoisting and Installation
4.3.1
For
Hoisting installation we need use pullbox for temporary hoisting during
erection the members.
-
Positioning
of lifting equipment, base conditions under out – rigger, operation circle,
etc. Shall carefully be examined before the work.
-
The
pullbox can change position depend the members will erect.
-
If
any abnormal parts are found, immediately pull down the member.
-
Proceed
with the wind – up and transfer operation slowly and carefully
-
Hoisting
work shall not be interrupted under any dangerous situation ( Example :
Interruption during hanging situation )
-
Installation
shall not be executed on rainy days, in strong windy or after sunset without
adequate lighting
4.3.2
Installation
of Body Tower
The First Installation is first
segment column and then the bracing. The first segment must starting with
correct elevation and correct distance. The good starting installation base on
first segment installation.
The bolts hole periphery conditions must be properly
examined before assembly. At that time, burrs and distortion around the edge
of the material should be carefully removed or detailed attention should be
paid to correctness.
4.4 Alignment and Leveling
To make sure the Tower standing with
stright and level.
Requirement spesification deviate
indicated with 0.125% of Height Tower for Alignment.
4.5 Bolt Tightening
After completing alignment and
Leveling continue to fastening and Tightening the bolts.
The final tightening shall be performed in accordance with the following
in order to obtain the standard bolt tensile strength.
The high strength bolts shall be
fastened using the torque
control methode.
After completing the fastening, verify the position
of the marking and as shown by cross painted at the nut.